Nokia PDM_2002001060 Exam Overview:
| Certification Vendor: | Nokia |
|---|---|
| Exam Name: | CPM - Certified Project Manager |
| Exam Number: | PDM_2002001060 |
| Exam Price: | Not officially published |
| Passing Score: | Not officially published |
| Available Languages: | English |
| Exam Duration: | 60 minutes |
| Certificate Validity Period: | Not officially published |
| Related Certifications: | Nokia Project & Portfolio Management Certification |
| Exam Format: | Multiple Choice, Scenario-based |
| Real Exam Qty: | 213-215 |
| Recommended Training: | Nokia Certified Project Manager Training |
| Exam Registration: | Nokia Training & Certification Portal |
| Sample Questions: | Nokia PDM_2002001060 Sample Questions |
| Exam Way: | Online proctored or authorized test center |
| Pre Condition: | Basic project management knowledge; no mandatory official prerequisites |
| Official Syllabus URL: | https://www.nokia.com/networks/training/ |
Nokia PDM_2002001060 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Project Planning & Scope Management | - Risk, quality and procurement planning - Schedule, resource and cost planning - Scope definition and work breakdown structure |
| Project Closure & Handover | - Financial closure and lessons learned - Contract acceptance and site quality review |
| Nokia-Specific Processes & Tools | - Vendor management and back-to-back principles - IPM, PCA, PARD and P-SQI metrics |
| Project Execution & Monitoring | - Cost adherence, earned value and KPI tracking - Change control and issue resolution - Team management and communication |
| Project Initiation & Business Case | - Business case definition and approval - Project charter and stakeholder identification |
Nokia CPM Sample Questions:
In which situation is it required to update/change the cost baseline?
- A. Change in subcontractor prices.
- B. Scope changes supported by a legal binding document.
- C. Roll-out delays affecting the original cost plan.
- D. When a risk has materialized.
Correct Answer: B 🗳️
When should lessons learned be performed?
- A. Only at the end of the project, during project closing.
- B. Only when there is time available as project managers have other priorities.
- C. After the end of the project, at the project post-mortem meeting.
- D. During the project execution and at the conclusion of the project.
Correct Answer: D 🗳️
Which of the following contract types places the greatest risk on the seller?
- A. Firm fixed price contract.
- B. Fixed price incentive contract.
- C. Cost plus incentive fee contract.
- D. Cost plus fixed fee contract.
Correct Answer: A 🗳️
An accuracy KPI has dropped significantly compared to previous periods. After some initial checks it turns out that the data is correct. What is the right way to proceed?
- A. Organize a meeting with NPO in order to make an action plan to improve.
- B. Communicate the deviation to the project stakeholders.
- C. Inform the CT head at the next CT meeting.
- D. Organize a meeting with key team members in order to identify root causes and make an action plan to improve.
Correct Answer: D 🗳️
Where should NCC be planned?
- A. Cost baseline (CBL).
- B. Estimate to completion (ETC).
- C. Risk contingency.
- D. Nowhere - NCC is always unplanned cost.
Correct Answer: B 🗳️