SAP E_ACTAI_2601 Exam Overview:
| Certification Vendor: | SAP |
| Exam Name: | SAP Certified - Project Manager - SAP Activate for Agile Implementation Management |
| Exam Number: | E_ACTAI_2601 |
| Exam Format: | Multiple Choice, Scenario Based |
| Passing Score: | 60% |
| Real Exam Qty: | 40 |
| Certificate Validity Period: | 5 years |
| Exam Duration: | 90 minutes |
| Related Certifications: | SAP Activate Project Manager |
| Exam Price: | USD 500 |
| Available Languages: | English |
| Sample Questions: | SAP E_ACTAI_2601 Sample Questions |
| Exam Way: | Online or at a Pearson VUE test center |
| Pre Condition: | None |
| Official Syllabus URL: | https://training.sap.com/certification/e_actai_2601-sap-certified-project-manager---sap-activate-for-agile-implementation-management-g |
SAP E_ACTAI_2601 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| SAP Activate Methodology Overview | 15% | - Agile Principles in SAP Activate - SAP Activate Methodology Phases - Key Deliverables and Milestones |
| Testing and Quality Management | 10% | - Test Planning and Strategy - Quality Gates and Acceptance - Test Execution and Defect Management |
| Project Planning and Preparation | 20% | - Risk and Issue Management - Project Planning and Scheduling - Project Scope and Requirements - Project Governance and Organization |
| Agile Implementation | 35% | - Backlog Management - Agile Estimation and Metrics - Agile Roles and Responsibilities - Sprint Planning and Execution |
| Fit-to-Standard and Customization | 20% | - Fit-to-Standard Workshops - Customization and Configuration - Integration with SAP Best Practices |
SAP Certified - Project Manager - SAP Activate for Agile Implementation Management Sample Questions:
1. Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct answers to this question.
A) End User Learning Needs Analysis
B) Project Plan
C) Change Management Roadmap
D) Detailed Design - Business Process
E) Learning Content
2. What are the SAP Cloud ALM Implementation capabilities? Note: There are 2 correct answers to this question.
A) Perform implementation activities
B) Natively built in test automation
C) Check data quality prior to migration
D) Monitor project performance centrally
3. Which estimation technique can be used in an Agile delivery approach to size the User Stories during sprint planning?
A) Leveraging effort estimates for similar User Stories from another Scrum team
B) Detailed bottom-up estimates that break each User Story into shorter tasks
C) Relative estimates in Ideal Person Days that reflect the best estimates provided by the project team
D) Detailed top-down estimates by the Scrum Master in story points or Ideal Person Days
4. In which phase do you create "an ordered list of everything that is known to be needed in the product"?
A) Prepare
B) Realize
C) Explore
D) Discover
5. What are some of the key topics covered in the Customer Team Enablement workstream? Note: There are 2 correct answers to this question.
A) Project management expertise
B) Process benchmarking expertise
C) Technology and architecture expertise
D) Business process expertise
Solutions:
| Question # 1 Answer: C,D,E | Question # 2 Answer: A,B | Question # 3 Answer: C | Question # 4 Answer: C | Question # 5 Answer: A,C |
We're so confident of our products that we provide no hassle product exchange.