APICS Certified in Planning and Inventory Management(Part 2) Sample Questions:
1. The approved output of the distribution requirements planning (DRP) process is an input to which of the following planningprocesses?
A) Strategic
B) Final assembly
C) Master production 0
D) Business
2. A supplier making a part with a specified dimension of 50 mm + 0.3 mm changes the tolerance range to + 0.5 mm. Which ofthe following pairs correctly identifies the changes to the percentage of defective parts and the process capability index?
A) The percentage of defective parts decreases, and the process capability index increases.
B) The percentage of defective parts increases, and the process capability index increases.
C) The percentage of defective parts increases, and the process capability index decreases.
D) The percentage of defective parts decreases, and the process capability index decreases.
3. Which of the following tools shows process changes and random variation over time?
A) Control chart
B) Check sheet
C) Pareto analysis
D) Histogram
4. When developing a quantitative model to support sales and operations planning (S&OP), which of the following statementsis most true?
A) Aggregation will be necessary to develop an appropriate model.
B) It is necessary to capture all of the detail in order to create a useful model.
C) A minimal level of effort is required to develop a model.
D) Clear objectives are not necessary to begin the modeling process.
5. A machine is suddenly having excessive downtime. Which of the following tools would be used in a root cause correctiveaction process to determine the problem?
A) Standardized work analysis chart
B) Balance chart
C) Failure mode effects analysis (FMEA)
D) A3 method
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: D | Question # 3 Answer: A | Question # 4 Answer: A | Question # 5 Answer: D |
We're so confident of our products that we provide no hassle product exchange.


By Patrick